Road Paving Schedule

Monday 12/13 – Milling Only – actual order for day TBD from the group below

  • Fredrick – Barrymore to John Mitchell
  • Emire/Empire – John Mitchell  to dead end
  • Frace Street – John Mitchell  to dead end
  • Susan -– John Mitchell  to dead end
  • Willever – – John Mitchell  to dead end
  • John Mitchell – Willever to Pickford
  • Ingersoll Ave – John Mitchell to Corliss – Skipping intersection of Grace and Corliss
  • Grace – Ingersoll to Pickford
  • Sargent – John Mitchell to Corliss

 

Tuesday 12/14– Milling Only– actual order for day TBD from the group below

  • Bowers Avenue – Belvidere Road to Frost
  • Ferguson Street Lincoln to Hillcrest (skip over intersection of Hagerty)
  • Barrymore (Lincoln to Hillcrest)
  • Barrymore (Burke to Fredrick)* – Limits may be reduced or omitted
  • Barrymore (Harte to Pickford)* – Limits may be reduced or omitted
  • Frost – Hillcrest to Barrymore – Not paving intersections just stopping just before curb return at Hillcrest and Barrymore

 

Wednesday 12/15– Milling Only

  • Hillcrest – Belvidere to Lincoln skip intersections at Barrymore, Frost

 

Thursday 12/16 – Paving Only

  • Hillcrest – Belvidere to Lincoln skip intersections at Barrymore, Frost
    • Depending on need contractor may pave into attached streets as needed

 

Friday 12/17– Paving Only

  • Bowers Avenue – Belvidere Road to Frost
  • Ferguson Street Lincoln to Hillcrest (skip over intersection of Hagerty)
  • Barrymore (Lincoln to Hillcrest)
  • Barrymore (Burke to Fredrick)* – Limits may be reduced or omitted
  • Barrymore (Harte to Pickford)* – Limits may be reduced or omitted
  • Frost – Hillcrest to Barrymore – Not paving intersections just stopping just before curb return at Hillcrest and Barrymore

 

Monday 12/20– Paving Only

  • Fredrick – Barrymore to John Mitchell (water service to be renewed first)
  • Emire/Empire – John Mitchell  to dead end
  • Frace Street – John Mitchell  to dead end
  • Susan -– John Mitchell  to dead end
  • Willever – – John Mitchell  to dead end
  • John Mitchell – Willever to Pickford
  • Ingersoll Ave – John Mitchell to Corliss – Skipping intersection of Grace and Corliss
  • Grace – Ingersoll to Pickford
  • Sargent – John Mitchell to Corliss

 

 

Tuesday 12/21 * weather permitting (This will only start if all prior days work is complete)

  • Milling – Lock Street – South Main/122 (just before the bridge to Ridge Street

 

Wednesday 12/22 * weather permitting

  • Paving – Lock Street – South Main/122 (just before the bridge to Ridge Street

 

Thursday 12/23/* weather permitting and subject to delays in prior work

  • Mill/Pave – Ivy Alley