Road Paving Schedule
Monday 12/13 – Milling Only – actual order for day TBD from the group below
- Fredrick – Barrymore to John Mitchell
- Emire/Empire – John Mitchell to dead end
- Frace Street – John Mitchell to dead end
- Susan -– John Mitchell to dead end
- Willever – – John Mitchell to dead end
- John Mitchell – Willever to Pickford
- Ingersoll Ave – John Mitchell to Corliss – Skipping intersection of Grace and Corliss
- Grace – Ingersoll to Pickford
- Sargent – John Mitchell to Corliss
Tuesday 12/14– Milling Only– actual order for day TBD from the group below
- Bowers Avenue – Belvidere Road to Frost
- Ferguson Street Lincoln to Hillcrest (skip over intersection of Hagerty)
- Barrymore (Lincoln to Hillcrest)
- Barrymore (Burke to Fredrick)* – Limits may be reduced or omitted
- Barrymore (Harte to Pickford)* – Limits may be reduced or omitted
- Frost – Hillcrest to Barrymore – Not paving intersections just stopping just before curb return at Hillcrest and Barrymore
Wednesday 12/15– Milling Only
- Hillcrest – Belvidere to Lincoln skip intersections at Barrymore, Frost
Thursday 12/16 – Paving Only
- Hillcrest – Belvidere to Lincoln skip intersections at Barrymore, Frost
- Depending on need contractor may pave into attached streets as needed
Friday 12/17– Paving Only
- Bowers Avenue – Belvidere Road to Frost
- Ferguson Street Lincoln to Hillcrest (skip over intersection of Hagerty)
- Barrymore (Lincoln to Hillcrest)
- Barrymore (Burke to Fredrick)* – Limits may be reduced or omitted
- Barrymore (Harte to Pickford)* – Limits may be reduced or omitted
- Frost – Hillcrest to Barrymore – Not paving intersections just stopping just before curb return at Hillcrest and Barrymore
Monday 12/20– Paving Only
- Fredrick – Barrymore to John Mitchell (water service to be renewed first)
- Emire/Empire – John Mitchell to dead end
- Frace Street – John Mitchell to dead end
- Susan -– John Mitchell to dead end
- Willever – – John Mitchell to dead end
- John Mitchell – Willever to Pickford
- Ingersoll Ave – John Mitchell to Corliss – Skipping intersection of Grace and Corliss
- Grace – Ingersoll to Pickford
- Sargent – John Mitchell to Corliss
Tuesday 12/21 * weather permitting (This will only start if all prior days work is complete)
- Milling – Lock Street – South Main/122 (just before the bridge to Ridge Street
Wednesday 12/22 * weather permitting
- Paving – Lock Street – South Main/122 (just before the bridge to Ridge Street
Thursday 12/23/* weather permitting and subject to delays in prior work
- Mill/Pave – Ivy Alley